Specification Compliance and Client Approval

Answering the real question first

If you work on public contracts, your first question is: “will the client accept this?”

The honest answer: stay-in-place formwork is a recognised and widely used method. Its use in culverts, however, depends on the project specification and the client's engineer. This page sets out the process and the documents required.

What MenfeX does not change

None of the following requirements are altered — all follow the project's structural design and specification:

  • Concrete class (min. C25/30 for cast-in-place)
  • Reinforcement layout and bar sizes
  • Concrete cover (50 mm)
  • Pour block and expansion joint rules (6 m / 12 m / 24 m)
  • Curing period
  • Cement selection in aggressive ground
  • Culvert geometry per the standard drawings

MenfeX changes the forming method only. The plastic is excluded from the structural section.

Approval steps

  1. 1

    Raise it early

    Bring it to the supervising engineer during the construction programme, not after award.

  2. 2

    Submit a technical file

    Product data sheet and material certificate, installation detail drawings, a statement that the formwork is excluded from the structural section, the installation guide, and the manufacturer's quality certificates.

  3. 3

    Trial installation

    A witnessed trial pour on site where required.

  4. 4

    Written approval

    Obtain approval in writing before production begins.

Certificates and documents

DocumentStatus
MenfeX product data sheetIn preparation
MenfeX material test reportIn preparation
MenfeX lateral pressure reportIn preparation
Installation detail drawingsIn preparation
No approval that has not been obtained is shown as obtained. Where a document is not ready, its status says so.

FAQ

Does leaving the formwork in place cause a structural problem?

No. The plastic is excluded from the structural section and carries no load.

The structural approach is the same as for the stay-in-place formwork systems already in wide use: the formwork is not a load-bearing element. Capacity is provided entirely by the reinforced concrete section, exactly as in a culvert cast with steel formwork. The design ignores the plastic.

Reinforcement layout and 50 mm cover follow the project's structural design — MenfeX changes neither.

Will the client's engineer approve stay-in-place formwork?

Stay-in-place formwork is a recognised method, but its use in culverts depends on the project specification and the client's engineer.

Be sceptical of any supplier who tells you it is unconditionally permitted. On public contracts, a change of forming method goes through the supervising engineer and is confirmed in writing.

Raise it during the construction programme, not after award. The technical file to submit and the steps to follow are set out on the Specification & Approval page. We support witnessed trial installations on site where required.

Request a trial installation

If you would like to trial the system on your contract, write to us about a witnessed sample installation.